Crashing (OM) for T-O-Y Inc: Critical path, completion, total

Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A to 3 weeks after crashing it.

Activity Total Normal Time (Weeks) Total Crash Time (Weeks) Total Normal Cost Crash Cost per period Immediate Predecessors
A 4 3 $2,000 $600 —
B 2 1 2,200 $800 —
C 3 3 500 $0 —
D 8 4 2,300 $750 A
E 6 3 900 $100 B
F 3 2 3,000 $1,200 C
G 4 2 1,400 $300 D,E

a) Using the normal time, what is the critical path, the project completion time, the total time required to complete all of the activities, and the slack time for each path?

b) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?

c) What is the maximum time that can be crashed? How much would the total cost increase?

d) Let’s return to the results found in a). Suppose the company believes that reducing the project completion time from the time reported in part a), will help the company realize an additional $500 per week in revenue. How many weeks should the company reduce the project completion time and what is the resulting cost of the project considering the additional revenue as an offset to the cost associated with crashing the project? The company is interested in selecting the path that minimizes the cost of the project.

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with AssignmentHelpWeb
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
Anthropology
Excellent services will definitely come back
Customer 452441, September 23rd, 2022
English 101
Very good job. I actually got an A
Customer 452443, September 25th, 2022
Nursing
The paper was EXCELLENT. Thank you
Customer 452449, September 23rd, 2022
Theology
Job well done and completed in a timely fashioned!
Customer 452451, November 18th, 2022
Business Studies
Thank you!
Customer 452451, November 27th, 2022
Architecture, Building and Planning
The assignment was well written and the paper was delivered on time. I really enjoyed your services.
Customer 452441, September 23rd, 2022
Psychology
Thanks a lot the paper was excellent
Customer 452453, October 26th, 2022
Anthropology
excellent loved the services
Customer 452443, September 23rd, 2022
Business Studies
Job well done. Finish paper faster than expected. Thank you!
Customer 452451, October 3rd, 2022
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat